Illustrative image – not actual.MMRDA is likely to commission Phase-II of Eastern Freeway by December 2013.
The developer is yet to construct more than 40 per cent of the slabs for the elevated section beyond Chembur, which will take the signal-free, toll-free road right up to Ghatkopar. Once it launches the slabs atop pillars, it will need about two months for finishing touches involving concretisation, black-topping, plastering, painting, illumination and erection of sign boards.
Launching activity is yet to be done in areas like Gautam Nagar, Panjarpol junction and at the other end of the elevated road near the Chembur-Mankhurd Link Road junction. The work was delayed as MMRDA obtained complete right of way for the 2.5 km Panjarpol-Ghatkopar Link Road only in May 2013, four years after construction started. For this area MMRDA had to rehabilitate 495 families.
The Eastern Freeway is being built in three segments and consists of a 9.3 km elevated road from Orange Gate on P D'Mello Road to Anik near Wadala, a 4.3 km road from Anik to Panjarpol near R K Films & Studios in Chembur, and the 2.5 km Panjarpol-Ghatkopar Link Road.
On 13 June 2013, MMRDA commissioned Phase-I of the project.
Related Link:
Project profile