Illustrative image – not actual.The MMRDA has sought an extension of loan from the World Bank (WB).
The authority has requested for an extension to complete the rail and road projects under the Mumbai Urban Transport Project (MUTP). It has made a presentation to the WB and has pointed out the problems that lie in two projects - the Virar Railway Car Shed and the Santa Cruz-Chembur Link Road (SCLR).
The said request is the third time that MMRDA has sought loan extension for the Rs 4,500-crore MUTP project which began in 2004. The second extension expires in June 2011.
All projects are expected to be ready by June except for the SCLR which will be completed in 2012.