The Mumbai Metropolitan Region Development Authority (MMRDA) has launched the final girder of Kalanagar flyover of Worli Sea Link to Bandra Kurla Complex (BKC).
With this, the crucial work related to the flyover has been completed. The flyover is expected to be open for traffic by the end of May 2021.
The new Worli Sea Link-BKC flyover is 725 mtr long comprising two lanes. The other flyover from Sion Dharavi Link Road towards the Sea Link will be ready by the end of November 2021.
At present, RPS Infraprojects, sub-contractor of Simplex Infrastructures appointed in January 2020, is carrying out the Kalanagar flyover construction work.
The entire cost of the project is Rs 103.73 crore. MMRDA, in a bid to decongest the Kalanagar Junction, is executing the construction of these flyovers.
Under this programme, three flyovers have been proposed -- one flyover starting from BKC to Worli Sea Link has already been opened for vehicular movement; the second from Sea Link to BKC will be open by May-end 2021; and the third flyover Sion Dharavi towards Sea Link will be ready by November-end 2021.
The work of the third flyover was affected due to the Metro Line 2B work, resulting in reduction in the scope of work and project cost by Rs 59.35 crore. The previous project cost was Rs 163.08 crore, which has now been reduced to Rs 103.73 crore.