MMRDA invites bids for residential permanent tenements in MumbaiIllustrative image – not actual.

The Project Management Unit of the Mumbai Metropolitan Region Development Authority has invited bids for the construction of the residential permanent tenements in Mumbai. The payment of the eligible party who executes the construction work will be done from the credit, which the Government of India has received from the International Development Association towards the cost of the MUT Project.

 

The bidding is open to both bidders, including international bidders who satisfy the criteria mentioned in the IBRD Guidelines for Procurement. Indian bidders should be registered in appropriate class with the Government of Maharashtra or other State Governments/ Government of India or State /Central Government Undertakings.

 

Details of the bidding can be enumerated as follows:

 

Package No.

Name of Work

Approximate value of works (Rs. in crore)

Period of Completion

I

Construction and handing over of 1442 residential tenements and 160 shops of  required size as per drawings and specifications with the built up area around 46,951.35 sq.m, each tenement of 20.91 sq.m.(225sq.ft.) carpet area, on plot bearing CTS No. 120 (Part) at Hariyali Village, Kanjurmarg. In addition to above, also construction of Society Offices, Balwadi & Welfare Centres (1073.42 sq.m. area).

 

The infrastructure work and amenities shall be as per Slum Rehabilitation Authority Policy of the State Government. 

42.3

15 months

II

Construction and handing over of 299 residential tenements, 8 shops of required size as per drawing and specifications with built up area around 9836.49 sq.m. on Plot bearing CTS No. 194 A (Part) at Ghatkopar Village, Ghatkopar (E). In addition to above, also construction of Society Offices, Balwadi & Welfare Centres (861.64 sq.m.area). The S1 building is varying carpet area from 20.910 sq.m to 51.09 sq.m. and for R1 & R2 building all tenements of 20.910 sq.m. carpet area.

 

The infrastructure work & amenities as per Slum Rehabilitation Authority Policy of the State Government.

11

15 months

 

The last date for the submission of Package I and Package II are 8 September 2003 and 9 September 2003 respectively. Further details can be had from the following address:

 

Mumbai Metropolitan Region Development Authority

5th floor, MMRDA Building, Bandra Kurla Complex

Bandra (East)

Mumbai- 400 051.

e-mail: mmrda@masbom01.vsnl.net.in