Illustrative image – not actual.Mumbai Metropolitan Region Development Authority (MMRDA) is considering public private partnership (PPP) model for two Metro Lines, Kanjurmarg-Badlapur and Mumbai Airport to Navi Mumbai Airport.
The nodal agency is considering either for PPP model or Swiss Challenge Method and after clearance from the state government, it will finalise one of the model.
Mumbai Metro’s first line between Ghatkopar and Varsova was built on PPP model by Reliance Infrastructure and MMRDA in joint venture (JV). The Reliance Infrastructure has 74 percent stake while remainder is held by the MMRDA.
The project was awarded in 2007 however, the actual work on the project began in late 2008. The metro was supposed to be completed by 2012 but due to permissions such as right of way, shifting of utilities and go-ahead from railways to cross over western line at Andheri, the project got delayed. Due to this, the cost of the project escalated from Rs 2,351 crore to Rs 4,321 crore.
Due to this, the arbitration over cost escalation and rise in fares currently heard by the courts.
Due to these issues, the MMRDA decided to develop Metro projects on its own. It is directly executing five projects worth approx Rs 45,000 crore, while it is executing Metro Line-3 between Colaba and SEEPZ through special purpose vehicle Mumbai Metro Rail Corporation and work on detailed project report of three more lines is underway.
The nodal agency is considering either for PPP model or Swiss Challenge Method and after clearance from the state government, it will finalise one of the model.
Mumbai Metro’s first line between Ghatkopar and Varsova was built on PPP model by Reliance Infrastructure and MMRDA in joint venture (JV). The Reliance Infrastructure has 74 percent stake while remainder is held by the MMRDA.
The project was awarded in 2007 however, the actual work on the project began in late 2008. The metro was supposed to be completed by 2012 but due to permissions such as right of way, shifting of utilities and go-ahead from railways to cross over western line at Andheri, the project got delayed. Due to this, the cost of the project escalated from Rs 2,351 crore to Rs 4,321 crore.
Due to this, the arbitration over cost escalation and rise in fares currently heard by the courts.
Due to these issues, the MMRDA decided to develop Metro projects on its own. It is directly executing five projects worth approx Rs 45,000 crore, while it is executing Metro Line-3 between Colaba and SEEPZ through special purpose vehicle Mumbai Metro Rail Corporation and work on detailed project report of three more lines is underway.