Illustrative image – not actual.The MMRDA, on 18 February 2012, conducted an electrical trial run of the Mumbai monorail, from Wadala to Mysore Colony - a distance of 4.5 km in Mumbai.
The Phase I of the project, from Wadala to Chembur, is expected to be completed by November 2012. The project is being implemented by MMRDA, with L&T and a consortium of Scomi Engineering. The project that will connect Wadala to Chembur (8.26 km) in Phase I and Jacob Circle to Wadala (11.28 km) in Phase II, will reduce travel time between the two localities from 90 minutes to 44 minutes. The project scope will involve design, construction, operation and maintenance (for three years) of the monorail system between Jacob Circle and Chembur. It is being done under an EPC contract.