The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 67 percent work on the Mumbai Trans-Harbour Link project. The project is slated to open by September 2023.
The authorities have accelerated the work to finish it eight months before the earlier deadline of May 2024. The bridge will provide a direct connect between South Mumbai and the under-construction Navi Mumbai International Airport.
A total of 1,089 pillars with a diameter of 1.8 mtr and 2.2 mtr are being constructed in all to prop up the bridge on the creek. The estimated cost of the project is Rs 17, 843 crore.
The work on the project commenced on March 2018. At present work on the deep section has been started.
The work is being executed in three packages – 10.4 km from Sewri-end, eight km from NhavaSeva-end and 3.6 km on land. The total length of the bridge is 22 km of which 16.5 km is in sea and 5.5 km on land.