Illustrative image – not actual.Mumbai Metropolitan Region Development Authority (MMRDA), on 16 October 2008, gave clearance to a 20 km route between Jacob Circle and Chembur via Wadala. The project will be implemented on BOT basis.
The work order of the proposed Rs.2,460 crore project will be issued to L&T-SCOMI by December 2008 and the work will start by January 2009. The first 10 km part from Jacob Circle to Wadala will be made operational in two-and-a-half years. The route will have 18 stations and each train will have four bogies. Work on the additional line will be completed within three years.
The L&T-SCOMI was asked to submit the revised bid document after it was found that it had quoted Rs.2,970 crore as the cost to be paid by MMRDA against the tendered cost of Rs.1,440.