MMRCL signs agreement with civil contractors of Metro-3Illustrative image – not actual.

The Mumbai Metro Rail Corporation (MMRCL) has signed agreements with four civil contractors who have been awarded the six packages. The agreement with the remaining one contractor will be signed shortly.

Earlier MMRC had issued the Letter of Award to five contractors with a total cost of construction of Rs 18,114.9 crore. The five companies that have been awarded contracts for the seven packages are as follows:

  1. L&T-STEC JV–Package-1 (Rs 2,988.53 crore). The stations in the package are Cuffe Parade, Vidhan Bhavan, Churchgate and Hutatma chowk.
     
  2. HCC-MMS JV – Package-2 – (Rs 2,521.89 crore) Stations - CST Metro, Kalbadevi, Girgaum and Grant Road.
     
  3. DOGUS-SOMA- Package-3 (Rs 2,557.84 crore) Stations - Mumbai Central, Mahalaxmi Metro, Science Museum, Acharya Atrey Chowk and Worli.
     
  4. CEC-ITD CEM-TPL JV – Package-4 (Rs 2,830.10 crore) Stations - Siddhivinayak, Dadar Metro and Shitladevi.
     
  5. Kumar-CRTG – Package-5 (Rs 2,817.02 crore) Stations - Dharavi, BKC Metro, Vidyanagari and Santacruz.
     
  6. J. Kumar-CRTG – Package-6 (Rs 2,118.40 crore) Stations - CSIA, Sahar Road and CSA International.
     
  7. L&T-STEC JV - Package-7 (Rs 2,281.45 crore) Stations - Marol Naka, MIDC, SEEPZ..


The actual work on the project will begin by October 2016.