MMRC completes tunnelling under Mithi channelIllustrative image – not actual.
The Mumbai Metro Rail Corporation (MMRC) has completed tunnelling below the main Mithi channel for Mumbai Metro-3.

Seven months after the work under the Mithi river started, MMRC has completed the tunnelling work.

By the end of March 2020, the twin tunnels will be ready across the entire 1.2 km wide river, which is constructing the 33.5 km Colaba-Bandra-Seepz underground network.

Presently, 85 percent of work (around one km) has been completed in one tunnel under the river and 65 percent (700 mtr) in the other.

The main Mithi channel, through which water flows through the year, is 270 mtr wide and during high tide, the entire stretch is filled with water. The tunnelling is in progress without any problems as a lot of preparatory work was done.

MMRC deployed Earth Pressure Balance Tunnel Boring Machines, which are especially used for operation in soft ground conditions containing water under pressure. It has used hydrophilic gaskets between Vidyanagari and Dharavi.

MMRC has set a deadline of December 2021 to commission the phase-I between BKC and Cuffe Parade.

Forty-one percent work has been completed on BKC station, being built under Mithi. It has adopted the cut-and-cover method for the station. BKC will be a three-line station with two main platforms and a crossover line which will connect to either sides of the mainline.

MMRC will be constructing three tunnels. Two stabling lines/sidings will facilitate reversal of trains during operations and for parking during non-operation hours; one stabling line on the south side of the station, under the Mithi river, and the other in the north side outside the river area.