On 7 December 2001, National Hydroelectric Power Corporation (NHPC) awarded a Rs.241 crore contract for electro-mechanical works of the 510 MW Teesta Stage-V hydel power project in Sikkim, to Mitsui & Co. Ltd of Japan.

 

The project, estimated to cost Rs.2,200 crore, is scheduled to be commissioned by March 2006. NHPC has already awarded all other civil and hydro-mechanical contracts for the project, to various companies.

 

The project is the biggest undertaken by NHPC in Sikkim. Its main components include a 95 metre high concrete gravity dam, 17.78 km long and 9.5 metre diameter horse shoe-shaped head race tunnel and an underground power house with three units of 170 MW each. According to NHPC, work on all the components of the project is going on as per schedule.

 