Illustrative image – not actual.The Mithi River development project of Mithi River Development and Protection Authority (MPDPA) is still waiting for financial assistance from the central government.
The Centre had assured financial aid to the project and accordingly the MPDPA had sent a proposal to the Centre in 2007, but the project has not yet received any financial assistance.
The project involves 17.83 km of Mithi's rejuvenation by deepening and widening the river, as well as its beautification. The work was split between the Mumbai Metropolitan Region Development Authority (MMRDA) and the Municipal Corporation of Greater Mumbai (MCGM). Of the total 17.83 km, 6.40 km has been taken up by MMRDA, while 11.43 km has been taken up by MCGM.
The project was expected to be completed by June 2010. It was delayed due to lack of coordination between MMRDA and MCGM, political interference, encroachment along banks, and coastal regulation zone restrictions.
MCGM and MMRDA have invested Rs 1,200 crore and Rs 400 crore in the project so far. While most of MMRDA's work has been completed, the work of MCGM has been facing hurdles due to encroachments along the riverbank.