Illustrative image – not actual.Shell India LNG's 2.5 million tpa import and regassification terminal at Hazira in Gujarat is experiencing some impediment that might delay commissioning by two months.
The project, which was to be commissioned in December 2004, will now be commissioned by March 2005, due to delay by its project managerial contractors.
The LNG teminal will be delayed by two months since its two managing contractors - Hazira Cryongenic Engineers, a French company and Hazira Marine Engineers - did not meet their contractual deadline.
Though the project is being delayed, Shell has already embarked on expansion plan to raise its LNG capacity to five million tonne per annum and eventually scale it up to 10 million tpa.
Shell has already set up two, 160,000 cubic meter of LNG storage tanks which will be later scaled up to four storage tanks and has set up 17 km of send-out pipeline to send gas to GSPL's gas grid.