Minjur desalination plant to be commissioned early next yearIllustrative image – not actual.

Chennai Water Desalination's 100 MLD sea water desalination plant at at Kattupalli in Minjur is expected to be commissioned by January 2009. Nearly 70 per cent of the work has been completed.

Dredging to facilitate laying of pipelines to draw sea water, from a depth of 10 m below sea level, and to discharge waste water will be carried out in September and October 2008. About 85 per cent of the work to lay a pipeline to Red Hills has also been completed. This includes completion of work on 18 km of the 23 km pipeline from Minjur to the Madhavaram pumping station.

The pipeline laying work, worth Rs.87.80 crore, is being taken up under the Jawaharlal Nehru National Urban Renewal Mission.