Illustrative image – not actual.Ministry of Environment and Forests has accorded environmental clearances for expansion of existing cement unit at Rajgangpur in Sundergarh district of Orissa. The expansion would result to enhance the capacity to 5 million tpa from the existing 1.5 million tpa. It would also include expansion of clinker capacity from 1.1 million tpa to 2.5 million tpa.
Holtec Consulting has prepared the detailed project report. Work on the project is underway with completion scheduled for December 2008.
OCL India is also setting up its first integrated steel plant in Orissa, scheduled for completion by September 2008. Company is also engaged in setting up cement units at Mania and Jagatpur in Cuttack district of Orissa.