Illustrative image – not actual.According to information tabled in Parliament, the Government has directed all the concerned ministries to provide adequate funds for the mega projects matching with their construction plan, in order to ensure timely completion.
Forty-five top
mega projects of Rs.1,000 crore and above are currently under implementation in
the central sector, with a total estimated cost of Rs.1,54,753 crore. The Centre
is receiving regularly, monthly flash reports on the progress of implementation
of these projects.
According to the Ministry of Statistics & Programme Implementation, nine
projects of Rs.100 crore and above, have either been dropped or frozen, after
incurring an expenditure of Rs.1088.78 crore, as on Ist April this year. The
total investment value of these projects were nearly Rs.10,600 crore. Frozen
projects are revived only when resources are available and other problems are
sorted out.
The unfinished projects are; the Barsingar Lignite Mine, Bikaner, the Barsingar
Lignite Thermal Power Station, Haldia Fertilizer Project, Midnapur, the Product
Terminal of Central India Refinery, Bina, the Petroleum Product Terminal of East
India Refinery, Paradeep, the Residue Upgradation Project of Gujarat Refinery,
the LPG Terminal of East India Refinery, Paradeep, the Koel Karo Hydroelectric
Project, Ranchi and the Farakka Super Thermal Power Project, Stage III,
Murshidabad.