Illustrative image – not actual.Mumbai International Airport (MIAL) is planning to expand the T2 terminal between 2016 and 2019.
The upgradation of the terminal involves a new taxiway and a tunnel under the runway for airside vehicular movement. The project will cost Rs 1,600 crore. It will also include expansion of the T2 by constructing the southeast pier that will let MIAL add seven passenger boarding bridges or aerobridges, thus taking the total to 29 bridges.
To implement this, MIAL will form an Airport Users Consultative Committee comprising airlines, Airport Authority of India (AAI) and other stakeholders.
Further, the proposed metro link to the airport, as part of the Colaba-Seepz line, will reduce the commute time between Colaba and the airport. In the airport, three stations have been planned -- one each at the domestic and international terminals and one in the GVK SkyCity, a commercial hub being planned on airport land.
The cost of the stations at the terminals will be included in the airport project cost, while that at the airport colony will be part of the SkyCity. The total cost of developing the metro lines in the airport is estimated at Rs 518 crore.