Illustrative image – not actual.Maharashtra Housing & Area Development Authority (Mhada), is planning to complete one building in the Dharavi revamp plan, by April 2014.
With the development plan of Dharavi yet to be finalised, Mhada had started the construction of one building in Sector-5, expecting to accommodate 358 eligible slum dwellers.
The state government has designated Mhada as the special planning authority for Sector-5 of Dharavi, which stretches over 65 ha, of which 24 ha is developable.
The authority commenced construction work for the project in February 2013. It has already received approval for 13 of the 18 floors. The building is complete till the ninth floor, while structural work has been completed till the 13th floor. Overall, the state housing board will build 9,600 tenements to rehabilitate slum dwellers in Sector-5. The 18-floor, C-shaped building will have 21 tenements on each floor connected by a long corridor.