Metro stations to be ready by DecemberIllustrative image – not actual.

The metro stations along Reach-I: M G Road to Byappanahalli in Karnataka are likely to be ready by December 2010.

Bangalore Metro Rail Corporation (BMRCL) is likely to complete about 85-90 per cent work on the six stations along Reach - I, by end-November 2010. All passenger amenities including lifts, escalators and staircases will be completed by then.

The six stations are - M G Road Station, Trinity Station, Ulsoor Station, Indiranagar/CMH Road Station, Swami Vivekananda (SV) Road Station and, Byappanahalli Station. According to sources, Byappanahalli and M G Road stations are likely to be the first two stations to be completed.

Work on the M G Road Station is about 70 per cent complete. The civil engineering structure is almost complete. Finishing touches are pending which includes flooring, painting, false ceiling and signboards. Nearly 80 per cent of the platform skeletal steel structure has been erected.

The Trinity Station is about 60 per cent complete. Civil structures have been completed. Currently, skeletal steel structure at platform is being erected and flooring work is underway.

About 60 per cent of skeletal steel structure at Ulsoor Station platform has been completed. Civil structure is almost complete.

Currently, erection of the steel skeletal structures has begun at Indiranagar/CMH Road Station.

Both the SV Road Station and Byappanahalli Station are 70 per cent complete. While painting and flooring work is underway on the SV Road Station, the steel structure is being erected over the platform and is almost complete at the Byappanahalli Station.