Illustrative image – not actual.Metro Railway’s project from Tollygunje to Garia in Kolkata may get further delayed as the construction of the pillars on Tolly's ‘nullah’ was not proceeding as per schedule. The delay has been attributed to the 2,500 hutments sprouting along the banks of the ‘nullah’.
The company has not been able to provide compensation to the encroachers for leaving the area. As a result, foundations for only 450 pillars of the required 3,000 pillars, have been laid. Reportedly, the West Bengal government has proposed to pay Rs.15,000 to each family as compensation.
The project, which was to be completed by 2003, has
already been delayed by eight months. The delay has also resulted in cost
escalation, taking the revised projected cost to Rs.954 crore.