Illustrative image – not actual.Chennai Metro rail commissions its first tunnel between two stations - Washermenpet and Mannadi - on 13 March 2013.
The 1.3 km tunnel which is part of the Washermenpet-Airport corridor along Anna Salai stretches under 750 buildings. Work on tunnelling began in October 2012 from Washermenpet. So far 958 rings, which act as the roof and the walls, have been fixed along the stretch. Metro rail will now lay tracks and install other facilities.
Meanwhile, tunnelling is underway to build a parallel tunnel along the same stretch to lay a second line. The second tunnel has reached 205 mtrs. Work on tunnels is also progressing under Poonamallee High Road. Soon work will start for tunnelling from Saidapet to Teynampet under Anna Salai.