Illustrative image – not actual.The state cabinet, on 19 March, approved the final escalated cost of Metro Phase-I, which now stands at Rs 13,845 crore. Also, the cabinet formally sanctioned the extended deadline for Metro’s commissioning to December 2015 from the earlier one of December end 2013.
Phase-I of the Metro project consists of two corridors -- north-south corridor (named Green Line) and the east-west corridor (named Purple Line). Green Line is from Nagasandra to Puttenahalli (24.20 km) and Purple Line is from Baiyappanahalli to Mysore Road (18.10 km).
From the initial project cost of Rs 6,395 crore in 2006, when the Metro was finalised for 33 km, to Rs 8,158 crore in 2010, the cost shot up to Rs 11,609 crore for 42.3 km in 2011 after a project review and extension of an additional nine km.
In 2003, the first Detailed Project Report (DPR) for the Metro was prepared for a total length of 33 km. This DPR, involving a total investment of Rs 6,395 crore, was approved by the Union government in 2006. A southern extension was approved by the Centre - 3.7 km for Rs 681 crore in 2010. A northern extension of 5.6 km was also added the same year at a cost of Rs 1,082 crore. Thus, the cost of Phase-I of the project, which formed 42.3 km, was revised to Rs 8,158 crore.
The project started in 2007, and in 2011 a review was done. As per the prevailing cost of construction, Rs 11,609 crore was approved by Union government.
The final cost by the end of December 2015 will be Rs 13,845 crore -- a Rs 2,236 crore increase from the 2011 cost. A substantial part of the cost escalation has been attributed to factors like requirement of additional land, compensations, increase in cost of inputs, and adverse foreign exchange rate fluctuations.