Illustrative image – not actual.The Western Railway (WR) on 2 June 2010 approved two concept designs for 180-mtrs railway over bridge (RoB) connecting Andheri West and East submitted by Mumbai Metro One (MMOPL). Thus clearing a major hurdle for the 11-km Versova-Andheri-Ghatkopar Metro One.
The WR has given clearance to both options - a composite steel-and-concrete substructure and a full RCC one. A detailed design is likely to be submitted soon. The total length of the steel bridge will be 183 mtrs -90 mtrs of it right over the tracks. It is likely to take at least nine months to complete work.
MMOPL has already begun work on both sides of the railway tracks. Now, with the final concept designs getting a clearance from the railways, work on the railway premises is expected to commence shortly.
The MMRDA holds a 26 per cent stake in the SPV - MMOPL - formed between itself and the Reliance Infrastructure-led consortium.