Metro Cinema subway delayed furtherIllustrative image – not actual.

The pedestrian subway near Metro Cinema in south Mumbai is likely to be opened to the public only by June 2007. The final commissioning appears ever-elusive given that as much as 70 per cent of physical project completion was achieved in March 2006, the original commissioning date.

After being delayed by nearly a year due to problems relating to shifting of underground utilities and managing busy surface vehicular traffic during the construction period, the Rs.18 crore subway project is now being dogged by apparently trivial issues.

As per the contract, the contractor, Michigan Engineers Pvt Ltd, is supposed to provide lighting inside the subway. The contractor submitted its proposal to the Municipal Corporation of Greater Mumbai, but it took the corporation over six months to decide in whose name the electric meter would be sanctioned, a spokesperson of the contracting company told ProjectsToday.

The project has to provide access to the physically challenged as per extant clauses of Asian Development Bank, one of the financing agencies. The proposal of constructing a ramp was cancelled and it was suggested to have electrically-operated lifts instead. However, there is no clarity as of now on which technology should be used or which agency would provide the final safety certification.

The contracting company has alleged that it has already suffered a cost overrun of 30 per cent and there is no foolproof cost-escalation clause in the original tender. The Metro Cinema subway, costing Rs.18 crore, is the largest of three pedestrian subway projects currently underway in Mumbai. The subway with nine access points - spread across Anandilal Podar Marg, JSS Marg, Kalbadevi Road, MG Road, LT Marg and Mahapalika Marg - aims at completely eliminating human traffic at the road-crossing areas.

Contractors have unanimously alleged that lack of co-ordination between participating entities - mainly Bhrihanmumbai Electricity Supply & Transport Undertaking (BEST) along with other utility providers, the traffic police department and municipal ward offices concerned - are taking the toll on other Mumbai subway projects as well. The pedestrian subway near the Siddhivinayaka Temple in south-central Mumbai's Prabhadevi area today stands only 15 per cent complete, in the face of its original completion date of April 2006. Completion is now envisaged only by May 2008. Another subway project at Veer Savarkar Marg in the Shivaji Park area of south-central Mumbai is likely to be partly-commissioned for traffic by March 2007, but not before having suffered its share of delays.