Illustrative image – not actual.The Maharashtra Electricity Regulatory Commission (MERC) has granted permission to Wardha Power Company (WPCL) to utilise Maharashtra State Electricity Transmission Company's (MSETCL) existing 220 kV Warora substation to evacuate power from its 270 MW Warora thermal power station.
Appropriately, MSETCL had earlier granted connectivity to WPCL via its proposed 400/220 kV Warora substation, which now is unlikely to be completed before December 2011.