Illustrative image – not actual.MEP Infrastructure, in a joint venture with Long Jian Road & Bridge Company, has emerged as the lowest (L1) bidder by the National Highways Authority of India (NHAI) for three road projects in Maharashtra.
The following projects will be developed on hybrid annuity mode (HAM):
1. Four-laning of Ausa-Chakur section of NH-361 from 55.835 km to 114.345 km (design length 58.51 km). The project will entail an investment of Rs 848.63 crore with a bid cost of Rs 2.70 crore from the first year of the date of commencement.
2. Four-laning of Chakur-Loha section of NH-361 from 114.600 km to 187.800 km (design length 73.345 km) entailing an investment of Rs 1001.10 crore with a bid cost of Rs 2.70 crore from the first year of the date of commencement.
3. Four-laning of Loha Waranga section of NH361 from 187.800 km to 244.369 km (design length 56.569 km). The road project will incur an expenditure of Rs 1,073.10 crore with a bid cost of Rs three crore.
The above projects have a construction period of two years from the date of appointment with a concession period of 15 years, excluding the construction period.