MEP Sanjose Mahuva Kagavadar Road, a subsidiary of MEP Infrastructure Developers, has achieved Milestone-1 for a road project in Gujarat.
The project involves four laning of Mahuva to Kagavadar of NH-8E from 100.100 km to 139.915 km (design chainage from 100.450 km to 140.470 km) (Package-III) in Gujarat, on hybrid annuity mode (HAM), under NHDP Phase-IV, as per the concession agreement.
The authority has paid the first milestone payment of 20 percent of the physical progress for the project on 12 December 2017, which is 79 days ahead of the scheduled date for the milestone, viz 28 February 2018.