Megha Engineering & Infrastructures (MEIL) has completed Phase-1 of Rs 4,000 crore project to use Ganga floodwaters to provide drinking water to water scarce cities of Bodh Gaya, Gaya, Rajgir in Bihar.
As part of the Gangajal Aapurti Yojana under the state government's Jal Jeevan Hariyali Mission, surplus Ganga river water flowing during July to October will be stored in huge reservoirs.
This water will later be processed to make it potable and supplied to the people of these cities around the year.
The project will be inaugurated by Bihar Chief Minister Nitish Kumar on 27 November 2022, in Rajgir and on 28 November 2022, in Gaya and Bodh Gaya.
MEIL has created massive infrastructure for the project that includes building an intake well-cum-pump house at Hathidah ghat in the Mokama area of Patna from where the Ganga waters will be lifted for supply to these towns.
The company has also constructed four pump houses at Hathidah, Rajgir, Tetar and Gaya and three storage reservoirs with live capacity of 9.915 million cu mtr at Rajgir, 18.633 million cu mtr at Tetar and 0.938 million cu mtr at Gaya.
As a part of the project the company has also set up two power substations of 132 kV /33 kV and 33 kV /11 kV capacities, laid a 151 km-long pipeline, built four bridges and a rail over bridge.
As part of the Phase-1 extension, plans are afoot to also supply water to parts of Nawada district by the end of 2023.