Meerut-Muzaffarnagar section to complete by MarchIllustrative image – not actual.

The four-laning of the Meerut (Uttar Pradesh)-Dehradun (Uttarakhand) section of NH-58 on BOT (Toll/Annuity) basis is underway.

As far as the four-laning of Meerut-Muzaffarnagar section is concerned, out of total length of 78.31 Km, four-laning of 74 km has already been completed. The project is likely to be completed by March 2011.

Meanwhile, the four-laning of Muzaffarnagar-Haridwar section and Haridwar-Dehradun section of NH-58 has been awarded to concessionaire Era-Sibmost on BOT (Toll) basis. The work is likely to commence in December 2010.