Illustrative image – not actual.The Unit-II was loaded to 400 MW, making it the fifth of the six Medupi units to be synchronised to the national grid. The plant which will also be the fourth largest coal-fired power plant is located in Lephalale, Limpopo.
It is a greenfield coal-fired power plant comprising six units rated in total at 4,764 MW installed capacity. It will be able to meet electricity needs of 3.5 million households in the country.
The first unit of the coal power station, near Lephalale Limpopo, went online and into operation in August 2015. The next step will be the testing and optimisation of the unit, resulting in the unit being able to generate full power of 794 MW of electricity feeding into the national grid for the country’s consumption.