Medupi Power Station in South Africa to be operational 2021-endIllustrative image – not actual.
Eskom’s Medupi Power Station in Limpopo will be fully operational by the end of 2021. Plans are afoot to make sure that there is enough electricity in the country.

The Medupi power plant is located in Lephalale, Limpopo. It is a greenfield coal-fired power plant comprising six units rated in total at 4,764 MW installed capacity.

Upon completion, Medupi Power Station is set to be the largest dry-cooled power station in the world. The boiler and turbine contracts for Medupi are the largest contracts that Eskom has ever signed in its 90-year history.

Originally conceived as Project Alpha, with only three units planned to total 2,400 MW, the design was changed at a late stage and doubled in size.

The boilers were envisaged to be supercritical in type, which will make them 38 percent more effective than other Eskom power stations.