Illustrative image – not actual.Consultancy
organisation Mecon, has bagged a contract from the West Bengal State
Electricity Board for the renovation, modernisation and up-rating (RMU) of stage
1 and capacity augmentation of both stage 1 and 2 of the Jaldhaka hydro
electric power project in Darjeeling district.
Stages 1 and 2 of the project consist of three 9 MW units and two 4 MW units, respectively. The capacity augmentation would be done by adding one more 9 MW unit to stage 1 and one 4 MW unit to stage 2. The Jaldhaka project utilises water from the Himalayan rivers.
Mecon is currently providing consultancy services for the renovation and modernisation of Unit 3 and 4 of the Hirakud power station of Orissa Hydro Power Corporation. Earlier, it had successfully conducted RMU studies of the Hirakud power station and Periyar, Sholayar and Kodayar power stations of Tamil Nadu Electricity Board.