Illustrative image – not actual.The MCGM will be re-inviting tenders for the Colaba waste water treatment facility (WWTF) project. Two months ago, the civic body had scrapped the Rs 124 crore tender for the project after finding irregularities.
The tender for the project is expected to be floated this week. BMC has changed the condition of getting a particular technology for setting up the plant. Earlier, one technology was allowed that led to monopoly. There are four different technologies for sewerage treatment plant. All of them can apply.
The plan of handling city's increasing sewerage is delayed since Municipal Sewerage Disposal Project (MSDP-2) has been massively delayed. The MSDP-2 will entail construction and upgradation of WWTFs at seven locations across the city.