The sewerage project is being implemented by sewerage and infrastructural development corporation of Goa (SIDCGL), with an investment of Rs 200 crore.
SIDCGL has undertaken only part of the Margao sewerage project as a portion of it is being handled by the PWD, under the Japan International Cooperation Agency (JICA).
SIDCGL’s scope of work includes laying a sewerage network covering Malbhat, Pajifond, Aquem, Costa ground, Vidyanagar etc. The total length of the network is around 50 km and the trunk main is around eight km.
As of now, the work of giving connections to houses in parts of Navelim — Rumdamol and Davorlim — has started. Work of laying the sewer line in main Navelim, Talaulim, Aquem-Baixo, Dicarpale has been tendered. Three work orders have been issued and work is in progress.