Approvals have been granted for the commissioning of the Margao-Chandor-Curchorem (Sanvordem) newly constructed double-track route of the South Western Railway (SWR). The Commissioner of Railway Safety (CSR) has granted authorisation for its opening. 
 
CRS has authorised the opening of commercial services of passenger and freight traffic on the newly-built double-line section between Margao and Sanvordem.
 
CRS had conducted trolley inspection of the double-tracked Margao-Curchorem Section as also speed trial run on the route, on 23 September 2021. The train had clocked a speed of 124 km per hour during the trial run. 
 
However, CRS has authorised a sectional speed of 90 km per hour on the Margao-Curchorem route.
 
The quality of track geometry in the newly-constructed double-tracked route by the Rail Vikas Nigam is of high quality and meets all approved standards. 
 
The authorised sectional speed of 90 km per hour for opening the section is the highest compared to that of other sections opened in recent years.
 
Moreover, CRS has allowed for the sectional speed to be increased to 100kmph subject to certain conditions. For the sectional speed to be further increased to 110 km per hour, the railways is required to seek CRS's clearance after compliance with certain stipulations mentioned in the authorisation and upon submission of the results of certain track monitoring runs.
 
The Margao-Chandor-Sanvordem section is likely to be commissioned by 10 October 2021.