Illustrative image – not actual.The pharma project is being implemented in three phases. Phase-I and Phase-II have been completed in January 2017 and March 2017 respectively. Talking to Projects Today the project head informed that work on Phase-III is nearing completion and will be ready by November 2018.
The formulation unit is being built at a cost of Rs 200 crore. The machinery required for the project will be sourced from Italy, USA, Korea and Germany.
EDGE Studios has been appointed as the contractor and architect, while IPS International is providing consultancy services for the drug formulations unit.