Mangalore Special Economic Zone Ltd (MSEZL), a JV between ONGC, Karnataka Industrial Areas Development Board (KIADB) and Infrastructure Leasing & Financial Services (IL&FS) is facing hurdles for its proposed SEZ project at Mangalore.
MSEZL is facing rigorous opposition from the landholders who are resisting acquisition of their lands. Therefore, the project which has already seen a delay of over one year is likely to be further delayed due to non-availability of the land required for the expansion.
As a statutory requirement, any multi-product SEZ needs to have at least 2,500 acre. Currently, MSEZL has acquired 1,800 acre in Phase I for around Rs 700 crore. It has notified another 2,000 acre in the villages of Permude, Kuthethoor, Tenka Ekkaru and Delanthabetta near Mangalore. However, according to the landowners, the compensation amount announced by the company is far below the market prices.