Mangalore Power Project: Revised PPA clearedIllustrative image – not actual.

Karnataka Power Transmission Corporation has reportedly cleared the revised power purchase agreement (PPA) 1,015 MW Nagarjuna power project coming up in Mangalore.

The revised terms included the earmarking of 100 MW worth of power for Power Trading Corporation, revised return on equity of 16 per cent on the basis of 80 per cent PLF against 68.5 per cent in the original PPA, and a reduction in the incentives to 0.4 per cent for every one per cent increase in the PLF beyond the new normative PLF.

With this clearance, almost all the milestones for achieving wet financial closure — the stage when institutions and banks are ready to disburse funds — were complete. It is the only private sector mega project that has so far completed the development risk stage.

Power Finance Corporation (PFC) is the lead arranger for the Rs 4,400-crore project. The consortium members for debt financing the project include Rural Electrification Corporation Ltd, HUDCO, Life Insurance Corporation, State Bank of Mysore, State Bank of Travancore, and Canara Bank. PFC is the lead arranger for the project debt, estimated at Rs.3,080 crore.

The project equity in Nagarjuna Power Corporation, estimated at Rs.1,320 crore is being brought in by the Nagarjuna Fertiliser group and associated companies. The promoter group is expected to hold 51 per cent while foreign investors (not yet finalized) would hold another 49 per cent.

The company already finalized BHEL as the engineering procurement and construction (EPC) contractor for the project and Simplex Constructions for the civil engineering component. The EPC component is expected to cost at least Rs.2,500 crore and the civil works another Rs.980 crore.

The first phase of the project, comprising 507.5 MW is expected to be commissioned 38 months after full financial closure and the second 42 months thereafter. This would imply, the sources said, the project commissioning would extend into the Eleventh Plan Period. Once the project is fully commissioned by  end-2007, the addition to the state grid would be at least about 7,600 million units per annum assuming a PLF of 85 per cent. The first year power tariff from the project is estimated at Rs.2 per unit.

Fuel supplies for the project have also been tied up with Australian suppliers. Coal requirement is estimated to be in the region of 1.5 million tpa assuming 80 per cent PLF and a calorific value of 6,000 kilocalories per kg.