Mangalore Port highway project to complete by March 2009Illustrative image – not actual.

Work on National Highways Authority of India's Mangalore Port highway project (New Mangalore Port Road Connectivity Project), in Dakshina Kannada is expected to be completed by March 2009. The total project cost of the project is estimated to be about Rs.196.5 crore.

The scope of work involves conversion of 37.5 km, having three national highways (nos. 17, 48 and 13), between Surathkal and B.C. Road Town into four lane roads.

Work on 17.3 km length highway on NH 17 is underway, of which four-lane work has been completed on a 11km stretch. Three flyovers at Surathkal, Kottara Chowki and Kuntikan are in the advanced stages.

The repair work (involving concreting of 13 curves) on the 37 km stretch of NH 48 at Shirady Ghat section, between Hassan and Mangalore, is partially completed. The stretch has been opened for movement of vehicles and some minor works, which are pending on the proposed stretch, will be completed by end June 2008.

Related Links:
Project profile

← All latest storiesBack to top →