Mangalore-Bangalore rail link to be commissioned by December 2004Illustrative image – not actual.

The railway link between Mangalore and Bangalore is scheduled for commissioning by December 2004. However, if funds for the project, which is estimated to cost Rs.300 crore, are made available earlier, then the project could be completed by March 2004.

 

The project is being implemented in 2 parts, viz. Bangalore-Hassan and Mangalore-Hassan-Arsikere. Of these the Bangalore-Hassan stretch has already been completed, while large stretches of the other part still remained incomplete.

 

According to the Union Minister of State for Textilies, Mr Dhananjaya Kumar, who also represents the Mangalore-Madikeri constituency in the Lok Sabha, efforts were being made to ensure that additional funds were provided for the work in the supplementary Budget in an attempt to expedite the project.

 

As of 31 March 2002, an amount of Rs.140 crore had already been spent. With the current Budget allocation of Rs.45 crore, work had started on the stretch covering 44 km from Mangalore to Kabaka-Puttur. About 45 per cent of the earthwork on this stretch had been completed in addition to completion of ballast work.

 

Further, 90 per cent of earthwork on the 42-km Kabaka-Puttur to Subrahmanya Road stretch has been completed and if the estimated cost of Rs.30 crore is allocated in the supplementary Budget, then the work is expected to be completed by June 2003.