Illustrative image – not actual.Work on the new integrated terminal building of Airport Authority of India's Mangalore airport at Kenjar village is likely to be completed by March 2009.
Currently, near 65 per cent of the work on the project is completed. The apron comprising three parking stands and two aero bridges has already been completed. Global tenders will be called soon for construction of the aero bridge.
While the new terminal is being built at Rs.150 crore, work on the new runway has been completed at a cost of Rs.55 crore. A sum of Rs 4 crore will be spent on arrival lounge and Rs.3.75 crore on taxiway. AAI has requested the Karnataka government to grant land for construction of the taxiway.