Manchukonda Agrotech setting up rice mill in KarnatakaIllustrative image – not actual.

Manchukonda Agrotech is setting up a rice mill at Growth Centre, in Raichur district of Karnataka.


A spokesperson for the company informed ProjectsToday (PT) that it was setting up a rice mill with a capacity of 36 tonne per hour over 12 acre in Karnataka.


Earlier, the company had decided to set up a plant with 25 tonne per hour capacity, at a cost of Rs 60 crore but now it has planned to set up a unit with 35 tonne per hour capacity, at a cost of Rs 75 crore.


At present, work on the project is underway. Around 75 per cent of the civil work has been completed and the remaining work is expected to be completed by January 2015.

 