Around 70 per cent work on Manali Petrochemical's 8.4 MW biomass power project in Chennai district of Tamil Nadu is complete.

The project entails Rs.41 crore investment will set up two 4.2 MW power units to be used for captive use. The contract for the project has been awarded to Cethar Vessels and the consultant for the project is Avant Garde Engineers & Consultants. Earlier, the project envisaged in 2005 was scheduled for completion by April 2007. The project got delayed almost for a year for various reasons and finally, civil work commenced during mid-2007. The project is now scheduled for completion by July this year.