Maheshwar project to be expeditedIllustrative image – not actual.

IFCI along with banks and other financial institutions would hold a meeting on 19 and 20 July 2004 in Mumbai to discuss the various issues relating to the 400MW Maheswar hydel project costing Rs.2,281 crore. The project is being promoted by Maheswar Hydel Power Corporation.

The financial institutions including IFCI, IDBI, LIC and Power Finance Corporation have expressed concern over the lack of progress in the project, as the project work has been at a standstill since October 2001. The institutional sources would review the status of the project.

Meanwhile the project cost has increased from Rs.2,234 crore to Rs.2,281 crore. The project is proposed to be financed by equity of Rs.750 crore to be raised from S Kumars (Rs.185 crore), Bhel (Rs.70 crore), IDBI (Rs.50 crore), LIC (Rs.30 crore) and GIC (Rs.15 crore) and Optionally Fully Convertible Debentures (OFCDs) of Rs.400 crore.

Debt equity ratio on the completion of the project would be 2:04:1 on the premise that the entire OFCDs would be converted into equity at par by November 2007 which is the expected date completion date for the project.

← All latest storiesBack to top →