Illustrative image – not actual.Lenders to the S Kumars' promoted 400 MW Maheshwar Hydel Project in Madhya Pradesh have asked the promoters to infuse the promised equity and clear their interest dues, before proceeding to the financial closure stage.
The lenders to the project, including IFCI, IDBI, Power Finance Corporation and the State Bank of India, have also asked for a cost revision exercise before finances for the much-delayed project can be tied up, it is learnt.
S Kumars equity contribution for the project is still short of commitments by Rs.82 crore. The project has been in limbo since the exit of the 49 per cent equity stakeholder, US-based Ogden Energy. S Kumars has been scouting for a strategic partner or for a domestic financial institution to plug the Rs 350 crore equity gap.
To expedite the financial closure of the project, the lenders had earlier decided on the issue of fully convertible debentures of around Rs 350 crore. The Madhya Pradesh government has already extended a guarantee for the proposed convertible debentures issue, which can be converted to equity at a later date, the sources said.
The project, which was initially supposed to have a debt-equity ratio of 70:30, would now have a higher debt component of around 85 per cent, following the issue of debentures to cover up the equity gap.
The initial equity portion of Rs 750 crore would come down to Rs 350 crore. This comprises Rs 103 crore already brought in by the S Kumars group, much lower than the originally proposed Rs 185 crore.
Apart from S Kumars, equity contributions of around Rs 165 crore have been leveraged from the Bharat Heavy Electricals, IDBI, Life Insurance Corporation and General Insurance Corporation, while another Rs 41 crore has had been brought in by contractors. The Rs 1,883-crore debt component was to be financed by a consortium of 14 banks and financial institutions through a mix of rupee-term loans and the proposed debenture issue.
S Kumars had replaced Siemens with Bhel for the supply of equipment to the project. The hydel project is a run-of-the river project and, therefore, involves minimum submergence.
The probable tariff from the project, as per estimates made earlier, was expected to be around Rs 3.67 per unit in 2005-06. In the same year, the cost of supply of the Madhya Pradesh State Electricity Board (MPSEB) was estimated at around Rs 4.25 per unit.