Recognising the need for a state-level
initiative in order to complement the efforts of the central government to
liberalise the power sector, the state government of Maharashtra announced its
new Power Policy on January 29, 1996, with a view to accelerate the development
and implementation of power projects in the State. The new policy is a reflection
of the further liberalization of the national power policy. The key features of
the new policy are summarized below.
The state government will identify and
offer projects for private investment. To ensure transparency, a competitive
bidding process would be followed through two sets of bids – a qualifying bid
and an electricity rate bid. The qualifying bid will evaluate the bidders on
technical competency and experience and the electricity rate bid will include
and evaluation of project costs and financing patterns.
For projects based on conventional fuels
such as naphtha, distillate oil and other petroleum products, the state
government will guarantee the purchase of up to 80 per cent of power generated
between 6:00 hours and 22:00 hours and 60 per cent of power generated between
22:00 hours and 6:00 hours. Levellised capacity charges at 17 per cent discount
rate would be permitted in 20-year bids.
In addition, the state government
policy on power provides several incentives to developers setting up power
projects using non-conventional sources of energy. These are summarized below:
The state government will encourage
small power projects using non-conventional energy sources such as wind, solar
energy, biomass, solid waste and bagasse and will commit to offtake power from
such projects at a levellised tariff of Rs.2.25 per unit, subject to an increase
of five per cent per annum after three years.
The state government will provide
assistance in identification and selection of feasible sites for wind power
through Maharashtra Energy Development Agency (MEDA). Further, MEDA will also
offer help to promoters in the purchase of private land for the project.
Power projects of up to 10 MW will be
approved directly by MEDA without further permission from the state government.
Wheeling and banking will be permitted at such rates determined by the
Maharashtra State Electricity Board from time to time. An exemption from electricity
duty will be available with respect to power generated through captive power
plants using renewable energy sources.