Illustrative image – not actual.The Maharashtra government is
considering setting up a 1,100 MW bagasse-based power project in the State, at
an estimated cost of Rs.4,000 crore. The project will be implemented by sugar
co-operatives of the State, in collaboration with BSES Ltd (formerly, Bombay
Suburban Electricity Supply).
The project, to be implemented in
three phases, is expected to be completed by October 2005. It is likely to
generate 800 MW of exportable surplus, with MSEB to be considered as the first choice.
In the first phase, to be completed by May 2001, 15 co-operatives would be able
to generate 300 MW. In the second and third phases, an equal number of
co-operatives would be involved in the project.
Forty-seven of the 62 sugar
co-operatives that had evinced interest in the project, have been shortlisted.
The co-operatives were shortlisted on the basis of a minimum crushing capacity
of 2,500 tonnes of sugarcane per day.
Three models of equity structure
are being considered. The first option entails BSES holding the entire equity
stake. In the second option, the co-operatives would hold the entire equity
stake. The third option is for BSES to hold 65 to 75 per cent of the stake,
leaving the rest to the co-operatives.
Talks are on with financial
institutions such as Power Finance Corporation, Hudco, Rural Electrification
Corporation, IL&FS, IFC and US Aid, for tying up funds for the project.