The Maharashtra government is confident of power capacity of over 5,000 MW that will become operational during 2006, easing the current power crisis situation.

Phase I of 740 MW of the Dabhol power project, being revived by an SPV called Ratnagiri Gas & Power Pvt Ltd, would be operational by March 2006, according to Maharashtra finance minister, Mr Jayant Patil. Phase II of 1,444 MW is likely to come online by December 2006.

Besides, the extension projects of Khaparkhed and Parli power stations would be operational by December 2006, together adding 3,000 MW to the state power grid.

For more stories on the Dabhol power project revival, use the following recursive link.

Dabhol power project revival: Petronet LNG roped in (09-Jan-06)

← All latest storiesBack to top →