Maharashtra govt to take over Mumbai Metro-I projectIllustrative image – not actual.

The Maharashtra government is planning to take over the 11 km Versova-Andheri- Ghatkopar Metro-I project or negotiate with Reliance Infrastructure following its demand for a three-fold increase in tariff due to delays in its commissioning.

 

The three km Versova-Azad Nagar stretch was to be commissioned in September 2013, but was delayed due to non-receipt of Central Railway Safety Commissioner's approval. It is now expected to be commissioned in December 2013, but it might be further delayed if the Mumbai Metropolitan Region Development Authority and Reliance Infrastructure-led Mumbai Metro One (MOPL) failed to arrive at an agreement on the rates.

 

Meanwhile, the 32 km Mumbai Line-II of Phase I of metro project, connecting Charkop-Bandra-Mankhurd is likely to be scrapped due to legal issues.

 

 