Illustrative image – not actual.The Maharashtra Coastal Zone Management Authority (MCZMA) has rejected the construction of two pumping stations at Mahul and Santa Cruz under the storm water drain augmentation project in Mumbai, Maharashtra.
The projects have been rejected citing the need to destroy mangroves spread over 6,000 sq mtr.
Both the projects are part of eight pumping stations that were proposed to be constructed under the Brihanmumbai Storm Water Drain (Brimstowad) project announced, to increase capacity of the drains.
Now, the Municipal Corporation of Greater Mumbai, the developer of the project, has decided to scout for other locations to accommodate these pumping stations.
At Mogra nullah, the project can be shifted to an adjoining land, but no such alternative is available at Mahul. Meanwhile, the corporation has asked consultants to redesign the entire project so that it can be submitted to the MCZMA for clearance.
A total budgetary allocation of Rs 180 crore was needed to complete the two projects. Once completed, the projects would have relieved Santa Cruz, Vile Parle, Chembur and Mahul of water-logging.
Of the eight proposed pumping stations, work on the Haji Ali and Irla projects was completed two years ago and work on Lovegrove and Cleveland Bunder in Worli has been delayed due to several onsite complications.